Mulund Dumpyard
      
    Proposed Project Execution
   
    
     
         
        
            
                - Estimated 70 Lac ton of Dump to be cleared in 6 years 
- 20 + 2 Modular Units to be installed on Site
- Each unit will process 400 Ton of Dump per day
- Each unit processes 10000 Ton in a month (26 Days) 20 units process 2 Lac ton in a month
- Process cannot be done during monsoon period 
- Effectively 16 lac ton of waste is processed in a year