Mulund Dumpyard

Proposed Project Execution

  • Estimated 70 Lac ton of Dump to be cleared in 6 years
  • 20 + 2 Modular Units to be installed on Site
  • Each unit will process 400 Ton of Dump per day
  • Each unit processes 10000 Ton in a month (26 Days) 20 units process 2 Lac ton in a month
  • Process cannot be done during monsoon period
  • Effectively 16 lac ton of waste is processed in a year